Rejection French-speaking chamber

Châtelet hospital: the new remedies law does not help Sogepar Construct, because the contract was advertised before it entered into force

Ruling nr. 206816 · 23 July 2010 · VIe vakantiekamer

Sogepar Construct sought suspension under extreme urgency of the exclusion of its tender for the refurbishment of the Châtelet hospital without setting out in its petition the facts showing serious harm that is difficult to repair; because the contract notice had been published on 16 September 2009 — before the entry into force on 25 February 2010 of the Law of 23 December 2009 that abolished that harm requirement — the old rules applied and the petition was inadmissible.

What happened?

The Intercommunale de Santé Publique du Pays de Charleroi (ISPPC) put out to tender a public works contract for the refurbishment and conversion of the Châtelet hospital. The contract notice was published on 16 September 2009. By decision of 8 March 2010 the ISPPC excluded the tender of Sogepar Construct. On 16 July 2010 Sogepar Construct sought suspension of that decision under extreme urgency. The case came before the acting president of the VIth vacation chamber, State Councillor Houyet, on 23 July 2010; first auditor and head of section Derouaux delivered a concurring opinion. The Council first examined which law applied. The Law of 23 December 2009 had inserted into the Law of 24 December 1993 a new book on reasons, information and remedies, including an Article 65/15 exempting anyone seeking suspension of a decision of a contracting authority from proving serious harm that is difficult to repair. That law entered into force on 25 February 2010 under Article 76 of the Royal Decree of 10 February 2010. But Article 7 of the law provides that contracts advertised before that date — or for which, absent publication, the invitation to request participation or to tender was sent before that date — remain subject to the rules in force at the time of the notice or invitation. Since the notice here dated from 16 September 2009, the new law did not apply, even though the exclusion decision itself was taken after 25 February 2010. Sogepar Construct therefore had to prove a risk of serious harm difficult to repair under Article 17(2) of the coordinated laws on the Council of State, and, under Article 16(2)(6) of the Royal Decree of 5 December 1991, set out in its petition the facts establishing that harm. The petition contained no such statement. The Council therefore declared it inadmissible, dismissed it and ordered Sogepar Construct to pay the costs, assessed at EUR 175.

Why does this matter?

This judgment falls within the transitional period of one of the major reforms of remedies in public procurement. The Law of 23 December 2009, transposing the European Remedies Directive 2007/66/EC, made it much easier for unsuccessful bidders to obtain suspension: the requirement to prove serious harm difficult to repair was dropped. But the legislator tied its application to the time the contract was advertised, not to the date of the contested decision or of the petition. A contract advertised in September 2009 thus remained entirely under the old regime, even for an exclusion decided only in March 2010. Anyone who overlooked this and drafted the petition on the basis of the new rules lost without the Council looking at the merits. The principle reaches beyond 2010: whenever procurement rules change, the transitional provision — usually the publication date — determines which law governs a pending procedure, including the procedural rules on remedies.

The lesson

In every dispute, first establish which law applies, and look at the transitional provisions of any new rules. In public procurement, the date of publication of the notice (or of the invitation to participate or tender) is usually decisive, not the date of the decision you are challenging. If in doubt, draft your petition so that it holds under both regimes: also set out the facts showing serious harm difficult to repair, even if you think you are exempt. For contracting authorities: record the publication date clearly in your file and, in a dispute, check whether the applicant has met the admissibility requirements of the applicable regime.

Ask yourself

Do you know the date on which the contract you are challenging was advertised, and which legal regime follows from it? Have you checked the transitional provisions of recent legislative changes before drafting your petition? Does your petition, to be safe, set out the facts showing harm, even if you believe you are exempt? And as a contracting authority: have you checked whether the petition meets the requirements of the law applicable to your contract?

About this database

The Council of State (Raad van State / Conseil d'État) is Belgium's supreme administrative court. In disputes over public procurement — from contract awards to tenderer exclusions — the Council of State is the final arbiter. The rulings in this database are summarised by TenderWolf in plain language, with practical lessons for tenderers and contracting authorities. View all rulings →