Raf De Vriese fails the price justification in Tielt: questioned item by item, you must answer item by item
Raf De Vriese submitted the lowest tender, at 851,208.85 euros, for road repair works in Tielt, Pittem and Moorslede, but was excluded because it could not concretely justify the abnormally low unit prices of six items; the Council of State refuses to suspend the award to Van Robaeys (932,608.63 euros), because a general justification, mere assertions and arguments first raised in the proceedings do not undermine the authority’s assessment.
What happened?
On 12 May 2016 the city of Tielt decided to launch an open tender for ‘Repair works on various roads in the Mid-West zone – phase 2’. It was a joint contract on behalf of Tielt, Pittem, Moorslede and Rio-Pact, with works on the territory of the three municipalities and Tielt acting as contracting authority. The contract was estimated at 1,063,071.00 euros excl. VAT, published in the Bulletin der Aanbestedingen of 1 July 2016 and governed by the special specifications ‘Tielt 15.01B’. At the opening on 26 August 2016 there were six tenders; Raf De Vriese was the lowest at 851,208.85 euros. The engineering firm assisting with the award asked it on 5 September 2016 for a price justification of six unit prices deviating 32.30% to 84.37% from the average: sewer pipes (item 5.a.1), their sand-cement encasement (7.a.1) and four items for the removal and processing of surplus soil (9.c.1, 49.a.1, 49.b.1 and 49.c.1). Raf De Vriese replied on 23 September 2016 with a ‘general justification’, an item-by-item justification and some concluding remarks. The award report of 14 October 2016 found that explanation unconvincing. For the sewers, the stated output of 50 running metres per working day was considered unachievable for longitudinal and transverse culverts of 5 to 10 metres at 14 locations in 4 streets in 3 municipalities. For the encasement, output was overestimated and volumes underestimated. The soil-removal prices (4 to 5 euros/m³) were far below those of the five other bidders and below the average of 10 to 15 euros/m³ in a recent tender, without accounting for the many small quantities to be removed from various sites. The unit prices were labelled ‘unacceptably low’, the tender was excluded as irregular, and on 25 October 2016 the municipal executive awarded the contract to Van Robaeys for 932,608.63 euros. Raf De Vriese was informed by letter of 7 December 2016 and applied on 21 December 2016 for suspension under extreme urgency. The Council of State followed the concurring opinion of auditor Thomas Maes and dismissed the application. The general justification did not show how its eleven general factors concretely lowered the price of the six items, and the authority did not have to assemble an item-specific justification itself from such a ‘menu’. For the sewers, there was only an unsupported assertion that the output was achievable, while the city stated that other contractors achieve 25 running metres per working day. The central location of the bidder’s own concrete plant and its ‘highly cost-effective transport method’ for surplus soil had not been raised in the price justification — for the soil items only a sub-unit price ‘separate removal return €3/m³’ was given — and could not be invoked for the first time before the Council. According to the city’s calculation, the material cost of the encasement under compliant execution was already 11 euros per unit, against an offered unit price of 8 euros. The criticism based on the 15% threshold started from a wrong premise: the total price was 14.85% below the average, but the tender was excluded for its unit prices, not its total price. The criticism of the additional arguments — problems in executing phase 1, speculative prices in Chapter 1 and the absence of certificates of good performance — concerned only superfluous reasons. Raf De Vriese pays the 200-euro roll fee and a procedural indemnity of 700 euros to the city of Tielt.
Why does this matter?
The judgment places the burden of proof in the price examination squarely on the bidder. A request for price justification is ‘a serious matter’: the bidder must justify the prices of the queried items specifically, concretely and with the fullest possible supporting evidence. General strengths — an own soil bank, a concrete plant, efficient logistics — only count if the bidder itself shows in figures how they lower the price of that very item. Timing matters just as much: what is not in the price justification cannot be held against the authority for not examining it, and is no longer taken into account before the Council of State. The judgment also shows how the structure of an award report can decide a case. Because the city based its exclusion principally on the item-specific reasons and expressly included the additional arguments as subsidiary, the bidder lost any interest in attacking those additional arguments, however well-founded they might have been. Finally, the Council clarifies that the item-by-item price examination and the examination of the total price (the 15% threshold of article 99, § 2, of the Royal Decree on Award) are two separate tracks: a total price just within the margin does not protect against exclusion for abnormal unit prices.
The lesson
If you receive a request for price justification as a bidder, treat it as the most important document of your tender. Answer item by item, with figures: outputs supported by site data or post-calculations, material quantities in line with the specifications, transport and disposal costs with quotes or own cost prices. Explicitly link each general strength to each queried item — the authority will not do it for you. Include everything you might later want to rely on: an argument you only raise before the Council of State does not count. For contracting authorities, this judgment is a manual for a robust award report: query the deviating items precisely, rebut the justification item by item with concrete, verifiable arguments (outputs, compliant volumes, other bidders’ market prices), and keep additional considerations — such as experience with the bidder on earlier sites — expressly subsidiary, so that the decision stands even without them.
Ask yourself
When asked to justify prices, do you justify each queried item separately and with figures, or do you rely on a general explanation about your company? For each general strength — own concrete plant, soil bank, transport organisation — do you show exactly how much it saves in the price of the item concerned? Have you really put everything in the justification that you might later want to invoke? Do you count on a total price just below the 15% threshold as protection, while your unit prices can be examined separately? And as an authority: does your exclusion decision rest principally on item-specific, verifiable reasons, and have you clearly marked additional arguments as subsidiary?
About this database
The Council of State (Raad van State / Conseil d'État) is Belgium's supreme administrative court. In disputes over public procurement — from contract awards to tenderer exclusions — the Council of State is the final arbiter. The rulings in this database are summarised by TenderWolf in plain language, with practical lessons for tenderers and contracting authorities. View all rulings →