A defensive stance in negotiations costs Sweco lot 1 at North Sea Port: 43% junior hours, a barely reworked BAFO and a lower score than in round one
The Council of State rejected Sweco Belgium’s extreme urgency application against the new award of lot 1 (‘Wet infrastructure Belgium’) of North Sea Port’s engineering services framework agreement to Tractebel Engineering, because the contracting authority was entitled to assess the BAFO on the degree of improvement relative to Sweco’s own first bid and to its competitors, Sweco largely ignored the objections raised orally about junior hours, port experience and an unrealistic case, there is no duty to provide a written negotiation note in advance, and the departures from the specifications — no explanation of the BAFO, no fixed BAFO deadline — did not harm Sweco.
What happened?
The port authority North Sea Port Flanders put out to tender, in the utilities sector, a framework agreement for engineering services in five lots, published in October 2021. Lot 1, ‘Wet infrastructure Belgium’, covered design, assessment and advisory work on quays, jetties, dolphins, bank protection and dredging. Specific specifications 2020-022 provided for a negotiated procedure with prior call for competition in phases. An initial bid had to obtain at least half the points on ‘team’ and ‘work plan’ to proceed; improved bids would be assessed on ‘the degree of improvement’ relative to the initial bids and to the other improved bids; and the final phase would consist ‘of an explanation of the bid by the tenderer, after which a best and final offer may be requested’. Tenderers quoted hourly rates per function and worked out a fictitious case: the design of a 200-metre quay with a retained height of 15 metres for 50,000 DWT vessels, including soil investigation and a permit file. Price counted for 40 points, team for 35, work plan for 20 and urgent ad hoc questions for 5. For lot 1, seven candidates were selected on 28 January 2022, four of whom submitted a bid. Sweco Belgium had already been invited by e-mail on 8 February 2022 to a negotiation meeting on 22 March, whereas it only submitted its first bid on 8 March. In the provisional assessment Sweco was well ahead with 70 points against 57 for Tractebel Engineering; on team and work plan it scored exactly the threshold of 17.5 and 10. During the meeting, according to the later report, North Sea Port raised among other things the limited experience with port-related structures, the profiles offered, the missing environmental and pile-driving analysis and the ‘unrealistic estimate of the case’. The report noted: ‘Tenderer adopts a defensive attitude and sticks to the bid submitted.’ After the BAFOs Sweco kept the full 40 points on price (Tractebel 19.14), but fell to 14/35 on team (Tractebel 30) and 8/20 on work plan (Tractebel 17.5); both scored 3.5 on ad hoc questions. Final score: Tractebel 70.14, Sweco 65.5. North Sea Port awarded the lot to Tractebel on 23 June 2022. Sweco sought suspension on 9 July, after which North Sea Port withdrew the award on 14 July to draw up a fuller report; by judgment no. 254.293 of 26 July 2022 the Council declared that application devoid of purpose. A new report followed on 23 September 2022, with the same scores but fuller reasoning, and on the same day a new award to Tractebel. Sweco returned to the Council on 8 October 2022. Its criticism of the lower scores got it nowhere. The specifications allowed the BAFO to be assessed on improvement, including in comparison with the others, and the report stated that several weaknesses ‘remained’ and that Sweco ‘largely disregards’ the comments. Sweco did not dispute the accuracy of the report on its negotiations and was therefore aware of the objections. The fact that it had added a reference matrix did not refute the finding that port experience remained limited for ‘certain profiles’. The Council considered the claim that the team consisted ‘mainly’ of juniors perhaps exaggerated, since seniors were also included. But Sweco deployed 284 junior hours on the case, 43% of the total input, and it was not unreasonable for North Sea Port to doubt on that basis whether it would be ‘relieved of concerns’ as requested. Sweco’s defence that the case was simple and that it worked efficiently amounted to an admission that it had not substantially revised its approach. The competitors’ confidential bids showed large differences in time allocated to, among other things, the environmental permit, the design and the drafting of the tender documents. Sweco’s argument that the others had made the case ‘unjustifiably more complex’ found no support in the file. On the work plan, the Council held that Sweco was setting its own views against the contracting authority’s express expectations. There is no duty to provide a written negotiation note before the negotiations: Sweco had received the comments orally and was not penalised on points that had not been raised. Nor did it show that being invited before its bid had arrived was to its detriment. The fact that the specifications provided for an explanation of the improved bid, whereas North Sea Port immediately requested a BAFO without further talks, was ‘perhaps not entirely in line with the letter of the specifications’. It did not harm Sweco, however, all the more so because its BAFO barely differed from the bid it had in fact explained. The Council also raised questions about the absence of a fixed BAFO deadline, since some tenderers might thereby have had more time than others. But Sweco had no interest in that complaint: it and Tractebel both negotiated on 22 March 2022, and Sweco submitted its BAFO later than Tractebel. There was no trace of negotiations with others after Sweco had submitted its BAFO. As in the parallel case on lot 2, the Council accepted a verbal assessment with an overall score as a method. A confidential internal assessment document proved that a provisional assessment had taken place before the negotiations. The fact that the report mentioned ‘differences in price quotation’ did not mean that there were abnormal prices: hourly rates were in line with each other, and hours were assessed under ‘team’, not in the price investigation. The Council rejected the application and ordered Sweco to pay the costs: 200 euros in court fees, a 24-euro contribution and a 770-euro procedural indemnity to North Sea Port.
Why does this matter?
Whereas the judgment on lot 2 (no. 254.975) mainly sets out the legal principles, this case on lot 1 shows how a negotiation is lost in practice. Sweco started with a thirteen-point lead and ended 4.64 points behind Tractebel. The reason was not a new defect, but the lack of any answer to objections the contracting authority had already raised orally. The evaluation report speaks of a ‘defensive attitude’, and the Council reads Sweco’s own defence — the case is simple, we work efficiently — as confirmation that the BAFO was not really revised. The judgment is also concrete about team composition. The specifications did not prohibit junior profiles, but 284 junior hours or 43% of the input could weigh on whether the contracting authority would be ‘relieved of concerns’. The judgment further clarifies what a tenderer may expect in the negotiation phase. There is no right to a written negotiation note beforehand or a report afterwards; oral comments suffice, provided the tenderer is not penalised on points that were never raised. Departures from the authority’s own specifications, such as skipping the explanation of the improved bid, and the absence of a fixed BAFO deadline visibly make the Council uneasy. They do not, however, lead to suspension as long as the applicant does not show that it was harmed by them. That interest requirement weighs heavily: Sweco itself submitted its BAFO later than the winner and could therefore not complain of unequal time. On price investigation, the Council confirms that ‘differences in price quotation’ do not in themselves raise a presumption of abnormal prices.
The lesson
Tenderers: a negotiation meeting is not a defence of your bid but an opportunity to improve it. Note every comment by the contracting authority and answer it point by point in your BAFO; a tenderer that ‘sticks to the bid submitted’ while the specifications assess the degree of improvement loses ground almost by definition. Be critical of the junior–senior ratio in the hours you allocate to a case, especially where the specifications put ‘relieving the client of concerns’ first. Do not wait for a written negotiation note, as you have no right to one. Ask for confirmation of the points discussed and, if no deadline is set, of the final date for your BAFO. If you want to rely on a procedural irregularity, show concretely how it harmed you, or the complaint will fail for lack of interest. Contracting authorities: follow the phasing your specifications announce, or state in advance that you will request a BAFO immediately after the negotiation meeting. Set the same BAFO deadline for all tenderers and record in an internal document, per tenderer and per criterion, your provisional assessment and the comments you made during the meetings. That record will be your main evidence if a tenderer later claims it did not know what was expected of it.
Ask yourself
After the negotiation meeting, have you listed every comment made by the contracting authority and visibly addressed it in your BAFO? What share of the hours for the case is performed by junior profiles, and can you justify that this is enough for the requested level of service? Does your team show demonstrable experience, profile by profile, with the type of infrastructure involved, such as port-related structures? Do you know the deadline for your BAFO, and have you had it confirmed if neither the specifications nor the contracting authority set one? As a contracting authority: does your negotiated procedure follow exactly the phases described in your specifications, including any explanation of the improved bid? As a contracting authority: have you set the same BAFO deadline for all tenderers and kept a verifiable record of each negotiation meeting?
About this database
The Council of State (Raad van State / Conseil d'État) is Belgium's supreme administrative court. In disputes over public procurement — from contract awards to tenderer exclusions — the Council of State is the final arbiter. The rulings in this database are summarised by TenderWolf in plain language, with practical lessons for tenderers and contracting authorities. View all rulings →