Rejection Dutch-speaking chamber

From 70 to 67 points after the BAFO: North Sea Port was entitled to score the SBE–MUC consortium lower than after the first round, and an award report rewritten after withdrawal is not ex post facto reasoning

Ruling nr. 254975 · 8 November 2022 · XIIe kamer

The Council of State rejected the extreme urgency application of the SBE Nederland – Ingenieursbureau MUC consortium against the new award of lot 2 (‘Wet infrastructure Netherlands’) of North Sea Port’s engineering services framework agreement to WSP Nederland: a tenderer admitted to negotiations after the provisional assessment has no right to a guaranteed starting score; a more detailed evaluation report drawn up after the withdrawal of a first award is not ex post facto reasoning for the new decision; a descriptive assessment in words with an overall score is not a prohibited method devised after the fact; hours per role may be assessed under the ‘team’ criterion; and an authority that sees no abnormal hourly rates need not carry out a specific price investigation.

What happened?

In October 2021 the port authority North Sea Port Flanders put out to tender, in the utilities sector, a framework agreement for engineering services divided into five lots: wet and dry infrastructure in Belgium and in the Netherlands, and rail in the Netherlands. Lot 2, ‘Wet infrastructure Netherlands’, covered design, assessment and advisory work on quays, jetties, dolphins, bank protection and dredging, among other things. Specific specifications 2020-022 provided for a negotiated procedure with prior call for competition, in successive phases. To proceed to the next round after the provisional assessment of the initial bids, a bid had to obtain at least half the points on ‘team’ and ‘work plan’; the improved bids would be assessed ‘on the basis of the degree of improvement’ compared with the initial bid and with the other improved bids. It was a price-list contract: tenderers quoted hourly rates per deployable function and applied them to a fictitious case to arrive at a total price. For lot 2, the case was the design of a 200-metre quay with a retained height of 20 metres, in a tidal area with a 4-metre tidal range, for 50,000 DWT vessels, including supervision and site management during a one-year execution period. Price counted for 40 points, team for 35, work plan for 20 and handling of urgent ad hoc questions for 5. On 28 January 2022 seven candidates were selected; six submitted a bid, all six were invited to negotiations and all six submitted a best and final offer (BAFO). In the provisional assessment of the initial bids, the SBE Nederland – Ingenieursbureau MUC consortium was well ahead with 70 points against 54.64 for WSP Nederland. After the BAFOs the positions were reversed. SBE–MUC kept the full 40 points on price, against 16.82 for WSP, but scored only 15/35 on team (WSP 31), 8/20 on work plan (WSP 18.5) and 4/5 on ad hoc questions (WSP 4.5). Final score: WSP 70.82, SBE–MUC 67. On 23 June 2022 North Sea Port awarded the lot to WSP. SBE–MUC sought suspension under the extreme urgency procedure on 7 July 2022. Because ‘the unsuccessful tenderers have more questions than expected’, North Sea Port withdrew the award on 14 July 2022, after discussion by its board, in order to draw up a clarified evaluation report; by judgment no. 254.292 of 26 July 2022 the Council declared the first application devoid of purpose. The new report of 23 September 2022 gave exactly the same scores, but with fuller reasoning. It now also contained the provisional assessment of the initial bids and a history of the negotiations. According to that report, North Sea Port had raised with SBE–MUC, among other things, the ‘far too low hours per role’, the limited replacement team and the ‘unrealistic estimate of the schedule’. The tenderer is reported to have replied that it wanted ‘to offer the lowest price to win the contract’, whereupon the contracting authority pointed to the price-quality ratio set out in the tender documents. According to the report, the case was not reworked in the BAFO and ‘the offer remains unrealistic’; the supervisor’s Dutch experience was too limited. That same day, 23 September 2022, North Sea Port again awarded lot 2 to WSP. SBE–MUC returned to the Council on 7 October 2022; WSP intervened. The first plea failed. The specifications required half the points on team and work plan only for admission to the next round, not again at the BAFO stage; there is no such thing as a ‘guaranteed starting score’, all the more so as improvement is also measured against that of the other tenderers. The reasoning was adequate: the fact that SBE–MUC could formulate substantive criticism contradicted its claim that it did not understand why it had received those points. Nor was the fuller reasoning ‘ex post facto’: the decision of 23 June 2022 had been withdrawn and is deemed never to have existed, and the new decision rested on a new report. The Council saw nothing unreasonable in the view taken of the supervisor, since the case was located in the Netherlands and, unlike the Belgian lots, included supervision and site management during execution. According to North Sea Port’s observations, that supervisor’s CV listed only one Dutch quay wall project, which appeared to be borne out by the confidential bids. The fact that the consortium had been selected was irrelevant, since selection and award serve different purposes. Hours per role could be assessed under ‘team’ because the specifications expressly asked for them there; the ‘price’ criterion looked at the total price, ‘team’ at the distribution of hours across roles. The second plea, on the assessment method, also failed. Referring to the Dimarso judgment, the Council recalled that an assessment method may in principle not be fixed after the bids have been opened. A descriptive evaluation in words, coupled with an overall score per criterion, is however a common method that fits within the assessment elements of the specifications. There is no obligation to draw up the written reasons for the provisional assessment before the negotiations. The file must, however, show that there was a provisional assessment; a confidential internal assessment document with comments from several evaluators, updated during the negotiations, showed that. Nor is the moment at which the course of the negotiations is put on paper decisive, as long as the record can be verified. The Council did question the fact that North Sea Port had set no clear deadline for the BAFOs, but SBE–MUC had no interest in that complaint: it was the last to submit its BAFO and the BAFO was found regular. The third plea, on the price investigation, failed too. The Royal Decree of 18 June 2017 distinguishes between the general price investigation, which must always take place, and the specific investigation, which is required only where prices appear abnormally low or high. The tenderers’ hourly rates were in line with each other, as the confidential file confirmed, so North Sea Port could reasonably find that there was ‘no indication’ of abnormal hourly rates. The Council rejected the application, allowed WSP’s intervention and reserved the costs.

Why does this matter?

The judgment answers a question that arises in every negotiated procedure: what is a good first-round score still worth? The answer is: little, if the specifications provide that BAFOs are assessed on the degree of improvement, including relative to competitors. SBE–MUC went from 70 to 67 points and WSP from 54.64 to 70.82, and for the Council that was not a sign of arbitrariness but the normal outcome of negotiations in which one tenderer took the contracting authority’s comments on board and, according to the report, the other did not. The second key point is the withdrawal. Contracting authorities that withdraw their award after a first urgent application and draw up a fuller report are often accused of inventing reasons after the event. The Council makes clear that the withdrawn decision is deemed never to have existed: the new decision stands on its own, and its reasoning is by definition not ‘ex post facto’. The judgment also refines the Dimarso line. Not every assessment without a previously published scoring scheme is prohibited; a verbal evaluation per criterion with an overall score remains permissible, as long as the contracting authority does not introduce a new, ordinal method after the fact. For the record of negotiations, what matters is verifiability, not when it was written down, and the Council accepts a confidential internal working document as proof of a prior provisional assessment. Finally, the judgment is useful for price-list contracts with a fictitious case. A tenderer that keeps its hours low wins on price but may lose on ‘team’ where the specifications expressly ask for hours per role. And as long as hourly rates are in line with each other, the contracting authority need not carry out a specific price investigation.

The lesson

Tenderers: a strong first-round score is not an acquired right. When the contracting authority raises concrete objections during negotiations — too few hours, too tight a schedule, too thin a replacement team — your BAFO must visibly address them, even if that pushes up your price. A ‘lowest price to win the contract’ strategy works poorly in a contract where quality counts for 60%. In a price-list contract with a case, check carefully under which criterion the hours are assessed; if the specifications ask for them under ‘team’, that is where they will be judged. In a second award after withdrawal, the argument that the new reasons were drafted ‘after the event’ will get you little; aim your criticism at the substance of the new assessment, and do not quote the reasoning selectively, since the Council looks at it as a whole. Contracting authorities: set out in the specifications how improved bids will be assessed and what a first-round threshold means. Keep an internal assessment document per tenderer and per criterion during the negotiations, and note which points were discussed with whom. Set a clear deadline for BAFOs; North Sea Port’s failure to do so raised questions. If an urgent application exposes weaknesses in your reasoning, withdrawing and deciding again on the basis of a fuller report is a legitimate course.

Ask yourself

In a negotiated procedure, do you know whether your BAFO will be assessed on absolute quality or on the degree of improvement relative to the first round and to competitors? Have you concretely addressed in your BAFO every objection the contracting authority raised during the negotiations? Under which award criterion do the specifications assess hours per role, and is your estimate realistic for the case? Do your key people, such as a site supervisor, have demonstrable experience in the country and with the practices where the case is located? As a contracting authority: does your file contain a verifiable record of the provisional assessment and of what was discussed with each tenderer? As a contracting authority: did you set a clear deadline for BAFOs and carry out a general price investigation that is apparent from the file?

About this database

The Council of State (Raad van State / Conseil d'État) is Belgium's supreme administrative court. In disputes over public procurement — from contract awards to tenderer exclusions — the Council of State is the final arbiter. The rulings in this database are summarised by TenderWolf in plain language, with practical lessons for tenderers and contracting authorities. View all rulings →